HOW TO CALCULATE THE CEMENT & AGGREGATE QTY FOR CONCRETE
take the ratio 1:1.5:3
cement =1
sand =1.5
metal =3
So what is the ratio we want to mixing 1+1.5+3=5.5
Volum of wet cement concret is 1.54 to 1.57
unit weight of cement bag is 1440 kg/cum
one bag of cement = 50/1440 = 0.034722 cum
SOLUTION : CEMENT = 1.54/5.5 =0.28
=0.28/0.0347 = 8.069 ( 8 bags)
one bag of cement =50 kg X 8.069 = 403.45 kgs.
SAND solution =0.28 X 1.5 = 0.42 Cum
1.5 is the mixing proportion
METAL SOLUTION = 0.28 x 3 = 0.84 cUM.
3 is the mixing proportion
1 Cum cement concrete is 1:1.5:3 ratio
cement = 403.45 kgs.
sand = 0.42 Cum.
metal = 0.84 Cum.
HOW TO CALCULATE CEMENT & SAND QTY FOR PLASTERING
10 feet= 3.05m
area of plaster = 3.05 x 3.05 = 9.3 m2
(convert thickness of plaster into m divide by 1000)
volume of plaster = 9.3 x (10/1000) = 0.09 m3
quantity of cement = 0.09/1+5 =0.09/6 = 0.02 m3
as cement comes in bags of 50 kg therefore volume of one
bag cement = o.0347 m3 (exact)
(or it may be taken 0.034 or 0.035 m3)
no. of cement bags = 0.02/0.0347 = 0.58 bags (almost 1 bag
of cement required for plaster )
quantity of sand = 0.02 x 5 = 0.10 m3
this is exact calculation
you can add 30% extra for wastage etc.
HOW TO CALCULATE CEMENT, SAND & BRICKS FOR BRICK MASONRY
Consider Brick Masonry for 1 cum with 1:5 ratio mix
1). Brick calculation
take brick size =200mmx100mmx100mm
convert in meter =0.2mx.1mx.1m
total volume of brick= .2x.1x.1=0.002 cum
calculate the numbers of brick for 1cum = 1cum/0.002cum= 500 numbers of bricks.
2). cement calculation
the ratio of cement mortar =1:5
sum =1+5=6
total dry mortar requried for 1 cum brick masonary=.30cum
so,
cement = (.30x1)/6= 0.05 cum
convert in KG=.05x1440=72KG
convert in cement bag= 72/50=1.44bag.
sand calculation
sand =(.30x5)/6=.25cum
convert in kg =.25x1440=360Kg.
to convert in cum
sand = .3*quantity of sand(5)/total of ratio
= .255 for one cum
take the ratio 1:1.5:3
cement =1
sand =1.5
metal =3
So what is the ratio we want to mixing 1+1.5+3=5.5
Volum of wet cement concret is 1.54 to 1.57
unit weight of cement bag is 1440 kg/cum
one bag of cement = 50/1440 = 0.034722 cum
SOLUTION : CEMENT = 1.54/5.5 =0.28
=0.28/0.0347 = 8.069 ( 8 bags)
one bag of cement =50 kg X 8.069 = 403.45 kgs.
SAND solution =0.28 X 1.5 = 0.42 Cum
1.5 is the mixing proportion
METAL SOLUTION = 0.28 x 3 = 0.84 cUM.
3 is the mixing proportion
1 Cum cement concrete is 1:1.5:3 ratio
cement = 403.45 kgs.
sand = 0.42 Cum.
metal = 0.84 Cum.
HOW TO CALCULATE CEMENT & SAND QTY FOR PLASTERING
10 feet= 3.05m
area of plaster = 3.05 x 3.05 = 9.3 m2
(convert thickness of plaster into m divide by 1000)
volume of plaster = 9.3 x (10/1000) = 0.09 m3
quantity of cement = 0.09/1+5 =0.09/6 = 0.02 m3
as cement comes in bags of 50 kg therefore volume of one
bag cement = o.0347 m3 (exact)
(or it may be taken 0.034 or 0.035 m3)
no. of cement bags = 0.02/0.0347 = 0.58 bags (almost 1 bag
of cement required for plaster )
quantity of sand = 0.02 x 5 = 0.10 m3
this is exact calculation
you can add 30% extra for wastage etc.
HOW TO CALCULATE CEMENT, SAND & BRICKS FOR BRICK MASONRY
Consider Brick Masonry for 1 cum with 1:5 ratio mix
1). Brick calculation
take brick size =200mmx100mmx100mm
convert in meter =0.2mx.1mx.1m
total volume of brick= .2x.1x.1=0.002 cum
calculate the numbers of brick for 1cum = 1cum/0.002cum= 500 numbers of bricks.
2). cement calculation
the ratio of cement mortar =1:5
sum =1+5=6
total dry mortar requried for 1 cum brick masonary=.30cum
so,
cement = (.30x1)/6= 0.05 cum
convert in KG=.05x1440=72KG
convert in cement bag= 72/50=1.44bag.
sand calculation
sand =(.30x5)/6=.25cum
convert in kg =.25x1440=360Kg.
to convert in cum
sand = .3*quantity of sand(5)/total of ratio
= .255 for one cum
Monday, 10 August 2015
Friday, 7 August 2015
REBAR NOTES TO SITE ENGINEERS
Following are the general points to remember for civil site
engineers to make the construction work easier while monitoring quality of
construction related to reinforcement work,
- Lapping is allowed for the bars having diameters more than 36 mm.
- Chair rod maximum spacing is 1.00m (or) 1 no per 1m2
- For dowels rod minimum of 12mm diameter should be used.
- Chairs minimum of 12mm diameter should be used.
- Longitudinal reinforcement not less than 0.8% and more than 6% of Cross C/S
- Minimum bars for square column is 4 no’s and 6 no’s for circular column.
- Main bars in the slab shall not be less than 8mm (HYSD) or 10mm (main bars) and the distributors not less than 8mm and note more than 1/8 of slab thickness.
- Minimum thickness of slab is 125mm ()
- Dimension tolerance for cubes + 2 mm
- Free fall of concrete is allowed maximum to 1.50m.
- Lap slices not be used for bar larger than 36mm.
- Water absorption of bricks should not be more than 15%
- PH value of the water should not be less than 6
- Compressive strength of bricks is 3.5 N/mm2
- In steel reinforcement binding wire required is 8 kg per MT