PROJECT METHODOLOGY


PROJECT METHODOLOGY
 what is project? What are its scope? What is the role & responsibility  for successful completion of a project ? Let me discuss in detail in a flow of methodology.

1. ESTIMATION (Quantity Survey) 
When a project is approved by a client for direct execution or any opening of a tender, estimation & quantity survey is the first procedure to calculate the boq, scope, spec, budget, material, margin, brand & other resources. The Estimation finalize the cost of a project. For good estimation to avoid the loss of cost after completion of a project, following methodology should be considered during estimation,

  1. 5% to 10% qty should be considered extra along with actual. Example if total concrete qty is 100 cum + 10% = 110 cum should be finalized. During execution it is best to control it within actual qty.
  2. 10% to 20% of rate should considered with present market material rate based on the completion of schedule. Example if the present cement bag rate is Rs. 400 + 20% = Rs. 480. Based on the past market study & experienced professionals it can be fixed.
  3. Over head costs like temporary site office building cost, fuel cost, transportation cost, site engineers or project employees salary should considered which is excluding the margin value.
  4. While preparing the estimation it is good to divide the estimation value stage wise for better budgeting of project.
Estimation is the base line for a project for fixing  the budget, spec, quality, stages of payment. It is best to do the estimation with a micro level stages. It is time consuming & little tedious, but it much helpful to calculate even a rate of small nail to forecast the project budgeting immediate during execution of any stages.

2. SCHEDULING
A Project without schedule is like a ship sailing without knowing its direction and destination. Scheduling of a project with start & end date of activities with its predecessors helps to plan the required resources, budget cash flow for the project, organization budgeting.

There are many scheduling software Primavera, MS Project available for advanced way of planning & scheduling the activity. But a good, systematic scheduling can be done by using MS Excel in a simple way as follows.
 
In the above image, a scheduling contains the description of works or work break down structure (WBS) , no of days for completion of an activity, start date & end date, in gantt chart view all the columns shows the calendar with month. In the graphical view of gantt chart , black color shows the planned schedule, green color shows the actual executed schedule, while vertical ash color shows the non-working days or Sunday’s. 

[ For format of scheduling to receive the soft copy of it, please feel free to email to subbiahinfrastructure@gmail.com ]

For better understanding about bar chart scheduling system one more illustration given above with few more details. As it is black horizontal line shows the planned schedule, green line shows the actual schedule, red line shows the no progress, while yellow line shows the delay or advance of completion of activity. Based on our idea & creativity, schedule reporting can be done any of our style.

3. PROCUREMENT  SCHEDULE
Other than the execution schedule, procurement schedule helps to remind to purchase the required resources on time as per the activity schedule, since material plays the major role for completion of project on time.

A procurement schedule can be made as follows
 
Based on the above fig for procurement bar chart, example shown for aggregates with activity qty wise & stage wise with delivery date of material 7 days before of the activity start date. It can be altered in any manner based on the planning engineer requirement. 

3. PROJECT MONITORING & CONTROL
After completion of estimation & scheduling, next is the major part of the project management is the execution of the project. The proper monitoring & controlling while executing the project because it should done within the estimated qty & planned schedule. The Project monitoring & controlling system can be made by implementing DPR (Daily Progress Report) system. The DPR should covers the follows :

  • Day progress measurement in LBD and total qty execution of day
  • Consumption of materials like cement, electrical,plumbing materials.
  • Manpower or Manday along with their workman ship (Example : if Brick work done, how many masons & helpers involved in the work qty of brick work done in how many hours of time.
Is it the work progress is as per the schedule, the future plans to complete the task and constraints or disturbances to complete the task as scheduled.
 

CONCLUSION
The motto of this article  is to guide fresher's and professionals in practical approach to understand site & project management.
 